At CTI, we take immense pride in our unwavering commitment to delivering outstanding customer service and pioneering solutions. Our dedication to excellence is not just a mantra; it's ingrained in the very fabric of our business.

TVA - Natural Gas Power Plant - Kiewit

TVA - Natural Gas Power Plant - Kiewit
Description
$2.2B 1450MW combined cycle power plant
Problem
Labor shortages
Product versatility
Schedule restrictions
Solutions
Intuitive: Quick connect tray system
Engineering Services: Step by step layout details
Schedule optimization: Delivered product by release
Consultations: Continuous application & schedule support

Tesla - Nighthawk - Rosendin

Tesla - Nighthawk - Rosendin
Description
$500M 300 MW Energy storage facility
Problem
Labor shortages
Skilled labor
Budget restrictions
Speed of installation
Rodent prevention requirements
Short circuit requirements
Solutions
Pre-Cut Lengths: Plug and play fitment
Engineering Services: Easy to follow installation details
Innovation: 2 bolt integrated unions
Coverage: Top and bottom protection
Custom brackets: Mitigate clearance issues

P66 Refinery - Hydrocracker Expansion - Phillips 66 & Cenovus

P66 Refinery - Hydrocracker Expansion - Phillips 66 & Cenovus
Description
$150M process unit upgrade leading to an increase in clean-product yield
Problem
Large environmental loads
Limited structural footprint
Labor shortages
Adaptability
Solutions
Engineering Services: Full detail packages
TSS: Reduced massive qty of supports required
TSS: Reduced system components by as much as 50%
TSS: Allowed immediate in-field modifications

Tesla - Data Center - Triad

Tesla - Data Center - Triad
Description
$800M Gigafactory expansion covering 1.4M sqft to support next gen AI development
Problem
Extremely short schedule
Non-standard sizes
Long lead time finishes
Labor shortages
Solutions
Engineering Services: Coordinated project schedule
Project Experience: Responsive application assistance
Alignment: Dedicated production for maximum output
Posi-Loks: Tool-less snap in splice
SRC: Tool-less Snap on retention clips

Honeywell - Aero Expansion - Capital Electric

Honeywell - Aero Expansion - Capital Electric
Description
$84M Aerospace manufacturing expansion covering over 500K sqft
Problem
Numerous certifications
Limited personnel clearance
Redacted drawing packages
Maximum product flexibility
Solutions
Extensive global certification portfolio
Direct point of contact to limit outside exposure
Prior experience with high level clearance projects
TT allowed easy modular onsite adaptability

Hersey - Liquids Plant - Guarantee

Hersey - Liquids Plant - Guarantee
Description
Multi-Million dollar cutting edge liquid processing expansion faciltiy, covering over 177K square feet
Problem
Critical Path Schedule
Consistent Labor
Specialty Hanging Requirement
Design & Layout
Solutions
CTI Project Planning: Priority & consistent delivery
No Thread Rod: ETO vertical mount solution
Eng. Services: Full layout & installation package

Panasonic - Battery Plant - Cupertino & Enerfab

Panasonic - Battery Plant - Cupertino & Enerfab
Description
$4 Billion electric vehicle battery plant Investment targeting 30 GWh annual production capacity
Problem
Engineering & Design
Labor Shortages
Accessibility to Hanger Locations
Access to Wire Mangement Expertise
Solutions
Engineering Services: Layout & Design
TOUGHLink: Intuitive & Accesible & Fast
TOUGHConnect: Continuous Attachment
CTI Team: Fast & Available to Assist

Leprino Foods - Dairy UG - Interstates

Leprino Foods - Dairy UG - Interstates
Description
$870 Million state-of-the-art dairy manufacturing facility with advanced re-gen electrification
Problem
Supply Chain Performance
Material Requirements
Washdown Requirements
Installation Methods
Solutions
CTI: Reduced Lead Times & Project Planning
304 SS: Full TM System wash down capability
Custom Design: Better wash down capabilities
Eng. Services: GA drawings & installation details

Samsung - Austin SCP- Yates

Samsung - Austin SCP- Yates
Description
$17 Billion semiconductor infrastructure investment focused on supporting tomorrows technologies
Problem
Tight schedule
Fixture Hanging Challenges
Simplicity of Installation
Solutions
EG & SS: Quick Turn
Custom Solutions: Designed & delivered in 3 weeks

Primrgy - Gemini - Kiewit

Primrgy - Gemini - Kiewit
Description
$1.2 Billion solar energy investment covering approximately 5000 acres
Problem
Tight schedule
Elevated basket for watershed with low clearance
Corrosive environment
Labor shortages
Solutions
TOUGHGalv: Quick turn / superior corrosion resistance
C2G Fittings: Removed weeks of cutting & splicing
Posi-Loks: Tooless snap in splice
Snap-On Covers: No loose hardware